Interior Progress



Interior taking shape with the walls and staircase framed in.
Great room area facing the back of the cabin






Kitchen area with beginnings of sink plumbing, countertop sample and cabinet style

Beginnings of the laundry room

Getting insulated

Upstairs bath/shower



June 8, 2016
Getting the ceiling insulated
Upstairs bedrooms


June 23, 2016, Preparations are underway to put the underlayment down for the tile in preparation for the cabinets to be installed June 24. Walls were also primed and painted.





June 24, 2016
Cabinets delivered and set! Thank you Gary and Danny, from Chuck's Custom Woodworks, Marshfield, MO.





















July 19, 2016
Carsiding being installed on the great room ceiling...will also be used as wainscoting.